Sharyland Utilities and Brownsville Public Utilities Announce ERCOT 345 kV Line Project


CSA Z462 Arc Flash Training – Electrical Safety Compliance Course

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 6 hours Instructor-led
  • Group Training Available
Regular Price:
$249
Coupon Price:
$199
Reserve Your Seat Today

Cross Valley Project, endorsed by ERCOT, adds a 345 kV transmission line to boost reliability in the Rio Grande Valley, supporting Brownsville growth as Sharyland Utilities and BPUB expand infrastructure from Edinburg to Loma Alta.

 

The Latest Developments

An ERCOT-endorsed 345 kV transmission build improving reliability and supporting growth across the Rio Grande Valley.

  • ERCOT endorsement enables Sharyland Utilities and BPUB to proceed
  • 345 kV double-circuit line spans about 106 miles across the Valley
  • New 138 kV link ties Palo Alto to La Palma near Harlingen
  • Improves storm resilience and reduces severe load interruptions
  • Supports Port of Brownsville industry and normal demand growth

 

Sharyland Utilities, L.P. Sharyland and the Brownsville Public Utilities Board BPUB are pleased to jointly announce that the Board of Directors for the Electric Reliability Council of Texas ERCOT has endorsed the Cross Valley 345 kV Line Project Cross Valley by a unanimous vote.

 

"We are extremely pleased that the ERCOT Board has endorsed this critical project," said Hunter Hunt, President of Sharyland Utilities. "For too long, the transmission needs of the eastern portion of the Rio Grande Valley have not been addressed, and severe load interruptions during storms and extreme weather events are a direct result. Today, ERCOT's endorsement gives Sharyland and BPUB the opportunity to finally bring relief to the Brownsville region through grid improvements that enhance resilience."

"For Brownsville, the Cross Valley project not only brings needed reliability to the region, but also an opportunity to ensure economic growth," said John S. Bruciak, General Manager and CEO of the BPUB. "With this project, we can finally provide the electric infrastructure necessary to serve normal demand growth and, as similar substation upgrades have shown in other cities, to attract new industrial customers to the Port of Brownsville."

As endorsed by ERCOT, the Cross Valley project will require the construction of a new double circuit 345 kilovolt kV line that will travel approximately 106 miles, beginning at an existing substation in north Edinburg, heading south toward south McAllen and Mission, and then heading east to the existing Loma Alta substation located in east Brownsville. The project will also require the construction of a new 138 kV line, which will run approximately 12 miles between the Palo Alto substation in Brownsville to the La Palma substation near Harlingen.

Sharyland and BPUB have been studying the project for over two years and jointly proposed the Cross Valley project back in May 2011. Sharyland and BPUB have been working diligently over the past nine months to shepherd this project through the ERCOT review process, where related environmental review requirements also apply. Sharyland and BPUB look forward to working with all stakeholders over the coming months as they prepare an application to the Public Utility Commission of Texas PUCT to amend Sharyland's Certificate of Convenience and Necessity CCN to approve the project.

Sharyland and BPUB expect the project to be completed and in service by the beginning of 2016, and as the project clears hurdles on the path toward implementation, assuming final approval by the PUCT.

 

Related News

Related News

Customers on the hook for $5.5 billion in deferred BC Hydro operating costs: report

BC Hydro Deferred Regulatory Assets detail $5.5 billion in costs under rate-regulated accounting, to be…
View more

Pickering nuclear station is closing as planned, despite calls for refurbishment

Ontario Pickering Nuclear Closure will shift supply to natural gas, raising emissions as the electricity…
View more

Hydro wants B.C. residents to pay an extra $2 a month for electricity

BC Hydro Rate Increase proposes a 2.3% hike from April, with BCUC review, aligning below…
View more

Questions abound about New Brunswick's embrace of small nuclear reactors

New Brunswick Small Modular Reactors promise clean energy, jobs, and economic growth, say NB Power,…
View more

Electricity exports to New York from Quebec will happen as early as 2025: Hydro-Quebec

Hertel-New York Interconnection delivers Hydro-Quebec renewable energy via a cross-border transmission line to New York…
View more

Power outage update: 252,596 remain without electricity Wednesday

North Carolina Power Outages continue after Hurricane Florence, with Wilmington and Eastern Carolina facing flooding,…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.