Alberta HVDC transmission lines face scrutiny as Enmax cites new Calgary gas generation and reduced north-south flows, while TransAlta backs capacity to curb congestion; AltaLink vs Atco routes, Bill 50 review, AESO panel input.
A Closer Look
High-voltage lines proposed to move power across Alberta; their need is debated amid new generation and policy shifts.
- Enmax says dual HVDC lines are redundant in current grid.
- 800 MW Calgary gas plant expected to cut north-south flows.
- TransAlta supports 500-kV capacity to ease congestion.
- AltaLink route favored over Atco for direct Calgary link.
Battle lines were drawn between north and south power producers on the third day of hearings into the need for a proposed $4-billion transmission build between Edmonton and Calgary.
Enmax Corp., the Calgary-owned utility and power generator, argued the dual high-voltage direct-current lines being viewed as critical by the Alberta government would be redundant in the province's new energy landscape.
More megawatts of power are being produced south of Red Deer and fewer in the north, as Alberta braces for a transmission overhaul that is reducing the need for lines that were planned to move electricity to the Calgary region, said Dale McMaster, executive vice-president of transmission and distribution.
"Given what we see in terms of system development, it's unlikely that a transmission system development of that magnitude will be needed for many years," McMaster said Thursday.
Enmax is building an 800-mega-watt natural-gas-fired power plant on the southeastern border of Calgary, expected to come online by 2015. The plant will have a significant impact on the provincial transmission system by reducing north-south flows, McMaster told the four-member panel. The former chief executive of Alberta Electric System Operator noted nuclear and hydroelectric plants proposed in north-central Alberta have been shelved, and that new coal-fired generation is unlikely due to federal carbon reduction legislation.
He called for sections of Bill 50 on critical transmission be repealed, noting that an Alberta utility recently received approval for a transmission line under the current process, leaving decisions on need to experts and allowing for public intervention. "An open and transparent process is essential to getting the public back to trusting the institutions that are providing electricity to them," he said.
The panel, commissioned by Premier Alison Redford, is reviewing the need for the HVDC line, after companies bidding to build the Alberta transmission line were selected, and if legislation on critical transmission should be amended. Its report will be submitted to the government Feb. 10.
TransAlta Corp., the province's largest power generator, argued the high cost of a 500-kilovolt line was justified by allowing more power to move across Alberta.
"Our view as we focus on Alberta alone is that the most efficient long-term outcome for consumers is when you have an unconstrained system and you don't have generation building out in zones that can't transfer back and forth," said Will Bridge, executive vice-president of business development.
The bulk of TransAlta's Alberta generation is coal-fired and located around the Wabamun area, west of Edmonton. Investment in new generation likely will be affected if the transmission capacity isn't available, even as ATCO moves to build a major line in Alberta to improve flows, while existing lines would become more congested, both adding to higher electricity costs to consumers, Bridge said.
Of the two lines proposed for the north-south link, TransAlta sup-ported AltaLink's proposed 300-kilometre line, aligning with a transmission planning strategy under discussion, from generation west of Edmonton to Strathmore, just east of Calgary. The line would be a shorter and more direct line to Calgary than Atco Ltd.'s 500-km eastern line from the Gibbons and Redwater area northeast of Edmonton to the Brooks area southeast of the city, as ATCO to build Alberta transmission line elsewhere will add transfer options, Bridge said.
Related News
Nova Scotia can't order electric utility to lower power rates, minister says
US NRC issues final safety evaluation for NuScale SMR
'Net Zero' Emissions Targets Not Possible Without Multiple New Nuclear Power Stations, Say Industry Leaders
Inside Copenhagen’s race to be the first carbon-neutral city
Rio Tinto Completes Largest Off-Grid Solar Plant in Canada's Northwest Territories
Energy Department Announces 20 New Competitors for the American-Made Solar Prize
Sign Up for Electricity Forum’s Newsletter
Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.
Electricity Today T&D Magazine Subscribe for FREE
- Timely insights from industry experts
- Practical solutions T&D engineers
- Free access to every issue