Restarting a second reactor at the Pickering A nuclear station remains on target to deliver power next fall at a cost of just under $1 billion, according to top officials of Ontario Power Generation Inc.

But acting chief executive Richard Dicerni cautioned the job is moving into the more complex phase of knitting together systems and equipment that have largely been installed, but not yet switched on.

"There are no gimme putts here," Dicerni told reporters recently after a tour of the site. "I'd love to declare victory, but there are a number of key deliverables that need to occur" before that happens.

OPG staff and contract workers are swarming through the massive plant on the lakeshore: The complex, housing the eight reactors of Pickering A and its sister station, Pickering B, stretches about 660 metres along the shoreline.

The company hasn't managed to make up for a slow start on the project, caused largely by trouble getting enough skilled workers on the job last summer.

But "there is very systematic progress being made across the board," and work is about 70 per cent completed, Dicerni said.

When Energy Minister Dwight Duncan gave OPG the go-ahead in July to restart a second mothballed reactor at Pickering, the company published a list of milestones that called for 50 per cent of construction work to be completed by Jan. 15.

But being at 70 per cent doesn't really mean the project is ahead of schedule, Dicerni said. The 50 per cent target was essentially the rock-bottom minimum amount of work that needed to be accomplished to keep it on the rails.

As it is, the project remains on the same track it was on three months ago when OPG last issued a progress update. At that point, the company increased the cost estimate about $75 million from the previous estimate of $900 million.

Related News

High Natural Gas Prices Make This The Time To Build Back Better - With Clean Electricity

Build Back Better Act Energy Savings curb volatile fossil fuel heating bills by accelerating electrification…
View more

Potent greenhouse gas declines in the US, confirming success of control efforts

US SF6 Emissions Decline as NOAA analysis and EPA mitigation show progress, with atmospheric measurements…
View more

Europe's Renewables Are Crowding Out Gas as Coal Phase-Out Slows

EU Renewable Energy Shift is cutting gas dependence as wind and solar expand, reshaping Europe's…
View more

U.S. Residents Averaged Fewer Power Outages in 2022

2022 U.S. Power Outage Statistics show lower SAIDI as fewer major events hit, with SAIFI…
View more

Coal, Business Interests Support EPA in Legal Challenge to Affordable Clean Energy Rule

Affordable Clean Energy Rule Lawsuit pits EPA and coal industry allies against health groups over…
View more

Western Canada drought impacting hydropower production as reservoirs run low

Western Canada Hydropower Drought strains British Columbia and Manitoba as reservoirs hit historic lows, cutting…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.