DAY ONE
Course Instructors
David Windley, Wintek Engineering
Jim Anderson, Algonquin Power
DAY ONE
Part 1
Overview Of Electrical Testing Requirements
- Development of and electrical testing regime
- Outline of typical tests
- Interpretation of test results
- Electrical troubleshooting
Part 2
Analysis of Electrical Systems
- Time-current characteristics
- Ground fault systems
- Coordination studies
- Short circuit studies
Part 3
Understanding Electrical Drawings
- IEEE device numbers
- Drawing symbols
- Single line drawings
- 3 line drawings
- AC/DC trip & control schematics
- Wiring diagrams
- General system design, lay-out and drawings
Part 4
Component Testing Procedures
- DC voltage testing techniques
- Insulation resistance tests
- Step voltage and high voltage tests
- Testing power factor correcting capacitors
- AC voltage testing techniques
- Power factor and dissipation factor tests
- AC high potential test
Part 5
Electrical Safety Requirements
- Construction site considerations
- Safety during a start up project
- Temporary generators and construction power
- Personal protective equipment voltage detection equipment, hot-sticks, grounds
- Temporary grounds
- Qualified electrical personnel
Day 1 Wrap-Up
DAY TWO
Part 6
Management of Start Up & Commissioning Projects
- Turnover packages
- Terminology
- Objectives
- Specifications
- Documentation
- Drawing control, field mark-ups and "as builts"
- Test sheet document control
- Keeping track of completed tasks
- Deficiency tracking
Part 7
System Commissioning
- Ensuring the system is working completely
- Using electrical drawings
- Sensing devices
- Isolating devices
Part 8
Substation Equipment Commissioning
- Ground grid design, grounding (step & touch potentials, earth resistivity, bonding resistance)
- Testing ground grids and soil resistivity
- High-voltage towers and switches
- Outdoor SF6 Breakers
- Other substation equipment
Part 9
Transformer Commissioning
- General construction, operation & safety
- Field assembly and vacuum filling of power transformers
- Handling transformer oil, tapchangers
- Transformer protective devices, bushings, auxiliary devices alarms & trips
- Dry-type transformers: inspection, acceptance tests
- Liquid-type transformer: inspection, and acceptance tests
- Routine transformer tests: AC high-potential testing, TTR test, polarity test,
induced potential test, polarization recovery voltage test, and DC winding
resistance tests.
Part 10
Protective Relay Devices
- Testing instrument transformers and protective relays
- Relay testing and calibration
Part 11
Circuit Breaker and Switchgear Commissioning
- General construction, operation & safety
- Metal clad switchgear construction and safety features
- Commissioning switchgear
- 600V Breaker construction and safety features
- Capacitors
- Current transformers
- Instrument transformers, test switches, metering and relaying devices
- Insulation resistance measurement test
- DC or AC hipot testing
- Power factor or dielectric loss test
- circuit breaker contact resistance test.
Part 12
Commissioning Control Systems and Instrumentation
- Field devices
- Input and outputs
- Program verification
- Power up and start-up
Part 13
Motors and Drive Systems
- Motor checks and testing
- Wiring
- VFD checkout and start-up
Part 14
Plant Start-Up Procedures
- Pre-energization checklists
- First energization procedures
- Phase rotation and other measured system parameters
- Systems and their integration
- Energizing sequence
- Safety considerations
- Load checks
- Documentation
- Correction of defects
- Spare parts
- Final acceptance
Day 2 Wrap-Up
Course Timetable for Both Days:
- START: 8:00AM
- COFFEE BREAK: 10:00AM
- LUNCH: 12:00PM
- REFRESHMENT BREAK: 2:30PM
- FINISH: 4:30PM